Location: Various
Value: $3,640,210
Contractor: Miller Paving Ltd.
Completion: Fall 2024
Status: Awarded
Project Manager: Scott Collin
Project Details:
This year's paving contract will complete complete asphalt repair on approximately 3 kilometres of roadway and 7 kilometres of surface treatment on rural roads; paving of the Terry Fox Trail, Crawford St. N., the Archie Dillon Sportsplex entrance, and the trail at Roy Nicholson Park.
The City bases its “grind and pave” priorities on feedback from internal departments like Public Works and from a 2019 Roads Needs Study, which has ranked roads based on a Pavement Condition Index (PCI).
Connecting Link |
FROM |
TO |
LANE |
|
McIntyre Rd. |
Hwy. 655 |
westbound fast lane |
|
Father Costello Dr. E. |
Father Costello Dr. W. |
eastbound fast lane |
|
McIntyre Rd. |
Father Costello Dr. W. |
eastbound curb lane |
|
McIntyre Rd. |
Father Costello Dr. E. |
eastbound both lanes |
Various Streets |
FROM |
TO |
WORK |
Cameron St. S. |
Wende Ave. |
Columbus Ave. |
grind and pave |
Father Costello Dr. |
Battachio St. |
Aura Lake Rd. |
grind and pave |
Government Rd. S. |
Riverside Dr. |
Carr St. |
grind and pave |
Pine St. S. |
Sterling Ave. |
Remi Cres. |
grind and pave |
Spruce St. S. |
Second Ave. |
Kirby Ave. |
grind and pave |
Victoria Ave. |
College St. |
Denise St. |
grind and pave |
Kraft Creek Rd. |
Airport Rd. |
Lefebvre Rd. |
grindings and surface treatment |
Jaguar Rd. |
Hwy. 101 W. |
Government Rd. S. |
surface treatment |
Mahoney Rd. |
Kamiskotia Rd. |
Sandy Falls Rd. |
grinding placement |
Ross Ave. |
Pine St. N. |
427 Ross Ave. |
grind and pave |
Gold Mine Rd. |
Shaw Creek Rd. |
Overpass |
grind and pave |
Kirby Ave. |
Mountjoy St. S. |
Birch St. S. |
grind and pave |
Theriault Blvd. |
Algonquin Blvd. W. |
Cameron St. N. |
grind and pave |